You can generate a Progress Claim at any stage of a Job. Progress Claims consists of two key steps – firstly creating the Progress Claim Sections and then generating Claims against these Section(s).
1. On the Job Card, choose the Progress Claims Tab then click the +Create New Section for Full Job Value button.
Alternatively, if you want to create a progress claim section for each of the job supplies, then you can click on + Create New Section for Each Job Supply.
If you chose Create New Section for Each Job Supply, the only difference is you'll have a few progress claim sections depending on how many supply items are added to the job but the rest of the steps would be the same. |
In this example, we select the option to Create New Section for Full Job Value.
2. A Progress Claim Section for the full Job value will be created and display in the Progress Claim Sections list. If required, you can rename it by clicking on the Section name and editing as needed. When ready, click the Save button.
1. To record a Payment that has been received against the Progress Claim, click the +Add Payment button to display the Add Payment pop-up window and accept a payment immediately in Ascora.
2. Enter the necessary details to process the payment.
1.To download the progress claim, click on Download Progress Claim, select your template, and click Download.
2. Open the downloaded progress claim document to see if all information are accurate and ready to be sent.
The following image shows a progress claim document that we've generated and it shows the percentage or value of the claim that we've selected which is 50%.
Once you're ready to send the progress claim to your customer, follow the steps below.
To delete a progress claim section, you must first delete the progress claim associated to that section.
1. To do it, click on Delete Progress Claim button and select Yes, delete this progress claim.
2. You can now delete the progress claim section by clicking the Trash Bin icon and select Delete.
We've now completed the process of generating a progress claim and its corresponding sub processes such as creating a claim, and adding a payment for Fixed Price or Time & Materials job.