Projects are your section-based or stage-based jobs which you can display by ticking the box beside "Projects Only" and clicking on the "Generate Gantt Chart" button.
You can also click on the black triangle beside the parent job to toggle the view such as hiding or showing the section jobs.
Moving or rescheduling the parent job automatically reschedules the job sections.
How to edit Start/End Dates & Completion Percentage
Double-click the job box and you'll see a pop-up box where you can edit the dates and completion percentage.
Adjusting the dates and completion percentage
...
Another way to adjust the completion percentage is to hover the mouse cursor over the box until you see the little triangle which you can drag right or left to adjust accordingly.
Adjusting the completion percentage by dragging the triangle icon
...
Note: You can connect as many tasks or projects as needed as it's not limited to connecting just two tasks or projects.
How to Create Creating Dependencies
How to Remove Dependencies
To remove dependencies between tasks or projects, click on the arrow and press the Delete key on your keyboard.
How to Remove Removing Dependencies
How to Resize the Gantt Chart
...
Note: You can drag it all the way across to the left side to completely hide the task list if preferred.
Resizing the Gantt Chart