Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Gantt chart is now available in Ascora to help manage your projects or jobs and also show the dependency relationships between projects /jobs and as well as the current schedule status.

There are a couple of ways to access the Gantt Chart, one is from the Scheduler → Project Gantt.

...

Here's an overview of the functionalities available in the Gantt Chart such as filter options, changing the view from weekly to monthly, adjusting task dates, and many more.

Image Removed

Displaying Projects Only

Image Removed

Image Added

How to Display Projects Only

Projects are your section-based or stage-based jobs which you can display by ticking the box beside "Projects Only" and clicking on the "Generate Gantt Chart" button.

You can also click on the black triangle beside the parent job to toggle the view such as hiding or showing the section jobs.


Image Added



(info) Moving or rescheduling the parent job automatically reschedules the job sections.

Image Added


How to edit Start/End Dates

...

& Completion Percentage

Double-click the job box and you'll see a pop-up box where you can edit the dates and completion percentage.

(info) Adjusting the dates and completion percentage

...


Another way to adjust the completion percentage is to hover the mouse cursor over the box until you see the little triangle which you can drag right or left to adjust accordingly.

Another way to adjust (info) Adjusting the completion percentage by dragging the triangle icon


How to Reschedule Tasks

You can drag and resize the tasks if needed by hovering the mouse cursor on the edge of the box until you see the double arrow which you can drag to reschedule the task or project. Alternatively, you   You can drag and drop to move a task or project to a different date.

How to Resize the Gantt Chart

Hover the mouse cursor on the grey vertical line right next to the % Complete column which automatically changes to a blue vertical line.

Drag to the left side to decrease the task list box.

Note: You can drag it all the way across to the left side to completely hide the task list if preferred.

Image Removed

Resizing the Gantt Chart

Image Removed


How to Create Dependencies

...

    Note: You can connect as many tasks or projects as needed as it's not limited to connecting just two tasks or projects.


How to Create (info) Creating Dependencies



How to Remove Dependencies

To remove dependencies between tasks or projects, click on the arrow and press the Delete key on your keyboard.

(info) Removing Dependencies

Image Added



How

...

to Resize the Gantt Chart

Hover the mouse cursor on the grey vertical line right next to the % Complete column which automatically changes to a blue vertical line.

Drag to the left side to decrease the task list box.

Note: You can drag it all the way across to the left side to completely hide the task list if preferred.

Image Added

(info) Resizing the Gantt Chart

Image Added