Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Another way to access Gantt Chart is to go to Reports and select Jobs Gantt Chart from the reports list.

...

Tip
titleNOTE

Only jobs with Expected Dates appear in the Gantt Chart. This can be added by accessing the job and add the Expected Date from the Job Details screen.


Gantt Chart Overview

Here's an overview of the functionalities available in the Gantt Chart such as filter options, changing the view from weekly to weekly or monthly, adjusting task dates, and many more.

Image RemovedImage Added


How to edit Start/End Dates and Completion Percentage

Double-click the job box and you'll be able to see a pop-up box wherein you can edit the dates and completion percentage and then click Save.

Adjusting Dates and Completion Percentage

...

Another way to adjust the completion percentage is to hover the mouse cursor over the box until you see the little triangle which you can drag right or left to adjust accordingly.


Adjusting

...

Completion Percentage



How to Drag and Resize Tasks

You can drag and resize the tasks if needed by hovering the mouse cursor on the edge of the box until you see the double arrow which you can drag to resize the task or project. Alternatively, you can also drag and drop to move a task or project to a different date.

...

Hover the mouse cursor on the grey vertical line right next to the % Complete column which automatically changes to a blue vertical line.

Drag to the left side to decrease the task list box.

...

To remove dependencies between tasks or projects, click on the arrow and press the Delete key on your keyboard.

How to Remove Dependencies

Image Added