You have two Jobs J120 with supply item worth $200.00  and J121  with the same supply item worth $200.00 and both suppliers supplies are under one supplier.

  • You create a PO on Job J120 and a unique PO number is assigned for a total amount of $200.00.
  • When you create a PO on Job J121, the same PO number will be assigned and amount increases to $400.00 by adding another supply for the same supplier.
  • This means that all open purchase orders for the same supplier are combined as per setting selected. 

...

3. Only On The Current Job Or Job Section - select this option if you only want to combine purchase orders on job level and if section based, on section level.

  • For example, if you have a job with Time & Materials as Pricing Method, and you have total of 5 supply items under one supplier, then they will be combined in one PO.
  • If you have Sections based jobs, and one section has 5 supply items under one supplier, then they will be combined in one PO.

     

4. Never - select this option if you want to never combine purchase orders.

...