(info)  Committed Supplies - is the total cost of all Purchase Order Lines created for Job Supplies marked as "Must Be Ordered."

                Example 1: If job supply has 10 quantities and you create a PO for all 10 quantities then Committed Supplies is for 10 quantities too.

                           Example 2: If job supply has 10 quantities and you create a PO for only 5 quantities then Committed Supplies is also for 5 quantities.
                                  Remaining 5 quantities remain as budgeted supply.

...

(info)  Actual Supplies - is the total cost of all Supplier Invoice Lines allocated and accepted for Job.

                          Example 1: If job supply has 10 quantities and you create a PO for all 10 quantities and received only 5 quantities in Supplier Invoice then Committed Supplies

...