        (info)  Budgeted Supplies - is the total cost of all Job Supplies which are needed to be ordered or the ones marked as "Must Be Ordered." 


        (info)  Committed Supplies - is the total cost of all Purchase Order Lines created for Job Supplies marked as "Must Be Ordered."

...

                Example 2: If job supply has 10 quantities and you create a PO for only 5 quantities then Committed Supplies is also for 5 quantities.
                                  Remaining 5 quantities remain as budgeted supply.


        (info)  Actual Supplies - is the total cost of all Supplier Invoice Lines allocated and accepted for Job.

...