        • Committed Supplies - is the total cost of all Purchase Order Lines created for Job Supplies marked as Must Be Ordered.

                             If job supply has 10 quantities and you create a PO for all 10 quantities then Committed Supplies is for 10 quantities too.

               If job supply has 10 quantities and you create a PO for only 5 quantities then Committed Supplies is only also for these 5 quantities.


        • Actual Supplies - is the total cost of all Supplier Invoice Lines allocated and accepted for Job.

...