        (info) Budgeted Supplies - is the total cost of all Job Supplies which are needed to be ordered or the ones marked as Must Be Ordered. 


        (info) Committed Supplies - is the total cost of all Purchase Order Lines created for Job Supplies marked as Must Be Ordered.

             If job supply has 10 quantities and you create a PO for 5 quantities then Committed Supplies is also equivalent to 5 quantities.


        (info) Actual Supplies - is the total cost of all Supplier Invoice Lines allocated and accepted for Job.

...